Whitney-Tisdale Lift Station Upgrades

Tuesday, July 22nd, 2014 – The City of Timmins wishes to advise residents of South Porcupine and Porcupine that we expect NAC to start mobilizing this week. The scope of […]

Tuesday, July 22nd, 2014 – The City of Timmins wishes to advise residents of South Porcupine and Porcupine that we expect NAC to start mobilizing this week. The scope of work for this phase of the project will include an entirely new lift station along with two storm water retention tanks. Over the next couple of months, the project will see a lot of activity such as excavation, site de-watering and concrete work. The project schedule is expected to span a period of 16 to 18 months.