TORONTO, ONTARIO-- Detour Gold Corporation is pleased to announce an updated life of mine plan for its 100% owned Detour Lake open pit mine in northeastern Ontario.
The new mine production plan supports a 21.7 year operating life with the current mineral reserves standing at 15.5 million ounces of gold (476 million tonnes grading 1.02 g/t Au). A National Instrument 43-101 ("NI 43-101") technical report for the updated life of mine plan will be filed today on SEDAR (www.sedar.com) and on the Company's website (www.detourgold.com). All figures are in Canadian dollars except where noted. Highlights- Detour Lake proven and probable open pit reserves of 15.5 million ounces contained gold
- 21.7 years mine life with mill throughput increasing from 55,000 to 61,000 tpd in 2017
- Life of mine average annual gold production of approximately 660,000 ounces at total cash costs of $723 per ounce sold(1)
- Next five years average annual gold production of approximately 600,000 ounces at a total cash costs of $759 per ounce sold(1)
- Life of mine sustaining capital of $1.14 billion plus $614 million for deferred stripping
- Undiscounted pre-tax net cash flow of $6.5 billion and undiscounted after-tax net cash flow of $5.1 billion
- Block A measured and indicated in-pit resources of 54 million tonnes grading 1.15 g/t, representing 2.0 million ounces of gold
Economic Assumptions |
Prior(1) (09/2012) |
Update (02/2014) |
|||
Gold price (US$/oz) |
$ |
1,200(2) |
$ |
1,200 |
|
Foreign exchange rate (US$/Cdn$) |
1.00 |
1.10 (3) |
|||
Electricity ($/kWh) |
0.065 |
0.05/0.08 (4) |
|||
Diesel fuel ($/l) |
0.92 |
0.95 |
|||
Income/mining tax rate (%) |
25/10 |
25/10 |
|||
Net Smelter Royalty (%)(5) |
2.0 |
2.0 (5) |
|||
Mine Parameters | |||||
Ore milled (Mt) |
470.0 |
476.4 |
|||
Waste mined (Mt) |
1,734 |
1,676 |
|||
Strip ratio (waste:ore) |
3.7 |
3.5 |
|||
Average gold grade (g/t) |
1.03 |
1.02 |
|||
Total contained gold (M oz) |
15.6 |
15.5 |
|||
Estimated gold recovery (%) |
91.0 |
92.2 |
|||
Total recovered gold (M oz) |
14.1 |
14.3 (6) |
|||
Mine life (years) |
21.5 |
21.7 |
|||
Average annual gold production (oz) |
657,000 |
660,000 |
|||
Costs | |||||
Sustaining capital ($ M) |
1,156 |
1,143 |
|||
Deferred stripping(7) ($ M) |
- |
614 |
|||
Total cash costs before adj. below(8) ($/oz sold) |
749 |
767 |
|||
Less deferred stripping adjustment(7) |
- |
(44 |
) | ||
Total cash costs(8) ($/oz sold) |
749 |
723 |
(1) | Refer to press release dated September 4, 2012 with Technical Report dated October 18, 2012. |
(2) | US$1,600/oz for 2013, US$1,500/oz for 2014, US$1,400/oz for 2015, and US$1,200/oz thereafter. |
(3) | Exchange rate of 1.05 for 2014, 1.07 for 2015, and 1.08 for 2016, and 1.10 for 2017 onwards. |
(4) | $0.05/kWh for 2014-19 and $0.08/kWh for 2020 onwards. |
(5) | 2% royalty is assumed to be paid in-kind. |
(6) | Includes approximately 58,000 ounces to be recovered from stockpiles as of December 31, 2013. |
(7) | The 09/2012 report excluded deferred stripping as the Company had not approved its deferred stripping accounting policy. |
(8) | Refer to the section on Non-IFRS Performance Measures at end of the press release. Total cash costs for 09/2012 based on gold ounces produced. |
Mineral Resources and Reserves (December 31, 2013) (5) |
Tonnes (Mt) |
Grade (g/t Au) |
Contained Gold (000's oz) |
||
Reserves (1), (2), (3) | ||||
Detour Lake Mine | Proven |
94.4 |
1.29 |
3,901 |
Probable |
379.7 |
0.95 |
11,585 |
|
P&P |
474.0 |
1.02 |
15,486 |
|
Stockpiles |
2.4 |
0.82 |
63 |
|
Total P&P |
476.4 |
1.02 |
15,549 |
|
Resources (1), (3), (4) | ||||
Detour Lake Mine | Measured (M) |
16.4 |
1.37 |
725 |
Indicated (I) |
65.9 |
1.01 |
2,150 |
|
M+I |
82.4 |
1.09 |
2,874 |
|
Block A | Measured (M) |
1.5 |
1.21 |
57 |
Indicated (I) |
52.5 |
1.15 |
1,934 |
|
M+I |
53.9 |
1.15 |
1,991 |
|
Total M+I |
136.3 |
1.11 |
4,866 |
|
Detour Lake Mine | Inferred |
19.2 |
0.75 |
465 |
Block A | Inferred |
2.5 |
1.23 |
99 |
Total Inferred |
21.7 |
0.81 |
564 |
(1) | Mineral reserves calculated using a gold price of US$1,000/oz; mineral resources calculated using US$1,200/oz. Foreign exchange rate of Cdn$1.03 to US$1.00. |
(2) | Mineral reserves estimated using a 4% dilution at 0.20 g/t Au (7% at 0.20 g/t Au for 2014) and 5% ore loss. |
(3) | Based on an elevated cut-off grade of 0.5 g/t Au for Detour Lake and cut-off grade of 0.6 g/t Au for Block A. |
(4) | Mineral resources are exclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. |
(5) | Totals may not add due to rounding. |
Years |
Ore Mined (kt) |
Ore Milled (kt) |
Head Grade (g/t) |
Production (oz) |
Waste (kt) |
Strip ratio |
2014 |
21,691 |
19,000 |
0.87 |
490,254 |
70,459 |
3.25 |
2015 |
22,942 |
20,075 |
0.91 |
542,610 |
78,455 |
3.42 |
2016 |
21,301 |
21,301 |
0.93 |
588,112 |
99,989 |
4.69 |
2017 |
22,265 |
22,265 |
1.04 |
684,832 |
107,166 |
4.81 |
2018 |
22,265 |
22,265 |
1.04 |
685,933 |
115,814 |
5.20 |
2019 |
22,265 |
22,265 |
0.83 |
542,560 |
119,136 |
5.35 |
2020 |
22,265 |
22,265 |
0.86 |
565,359 |
119,596 |
5.37 |
2021 |
22,265 |
22,265 |
0.95 |
627,201 |
118,082 |
5.30 |
2022 |
22,265 |
22,265 |
0.88 |
577,384 |
112,970 |
5.07 |
2023 |
22,265 |
22,265 |
1.01 |
668,434 |
105,940 |
4.76 |
2024 |
22,265 |
22,265 |
1.00 |
658,966 |
87,844 |
3.95 |
2025 |
22,265 |
22,265 |
1.02 |
670,201 |
79,344 |
3.56 |
2026 |
22,265 |
22,265 |
0.89 |
582,933 |
74,536 |
3.35 |
2027 |
22,265 |
22,265 |
0.99 |
650,690 |
73,869 |
3.32 |
2028 |
22,625 |
22,265 |
1.11 |
731,842 |
72,571 |
3.26 |
2029 |
22,265 |
22,265 |
0.99 |
655,740 |
62,596 |
2.81 |
2030 |
22,265 |
22,265 |
1.12 |
741,684 |
63,397 |
2.85 |
2031 |
22,265 |
22,265 |
1.09 |
719,348 |
53,555 |
2.41 |
2032 |
22,265 |
22,265 |
1.24 |
822,519 |
25,932 |
1.16 |
2033 |
22,265 |
22,265 |
1.24 |
823,485 |
22,672 |
1.02 |
2034 |
22,265 |
22,265 |
1.25 |
828,874 |
10,269 |
0.46 |
2035 |
7,320 |
15,293 |
1.05 |
474,499 |
1,557 |
0.21 |
Total |
474,024 |
476,439 |
1.02 |
14,333,459 |
1,675,751 |
3.54 |
Life of Mine |
$/t milled |
$/t mined |
$/oz sold |
|
Mining costs |
11.55 |
2.56 |
392 |
|
Processing cost |
7.82 |
- |
266 |
|
General and administration |
2.44 |
- |
83 |
|
Sub-total |
21.81 |
- |
741 |
|
Other adjustments |
- |
- |
(18 |
) |
Total cash costs (LOM) (1) |
- |
- |
723 |
(1) | Other adjustments include costs for deferred stripping, agreements with Aboriginal communities, refining charges and are net of silver by-product credits. |
Sustaining Capital |
Period 2014-18 ($ millions) |
Life of mine ($ millions) |
Mining |
168 |
535 |
Process plant |
71 |
126 |
Tailings management |
203 |
454 |
G&A |
14 |
28 |
Total |
456 |
1,143 |
Mine closure |
70 |
|
Deferred stripping |
226 |
614 |