Skip to content

Detour Gold Updates Life of Mine Plan for Detour Lake

TORONTO, ONTARIO-- Detour Gold Corporation is pleased to announce an updated life of mine plan for its 100% owned Detour Lake open pit mine in northeastern Ontario. The new mine production plan supports a 21.

TORONTO, ONTARIO-- Detour Gold Corporation is pleased to announce an updated life of mine plan for its 100% owned Detour Lake open pit mine in northeastern Ontario.

The new mine production plan supports a 21.7 year operating life with the current mineral reserves standing at 15.5 million ounces of gold (476 million tonnes grading 1.02 g/t Au). A National Instrument 43-101 ("NI 43-101") technical report for the updated life of mine plan will be filed today on SEDAR (www.sedar.com) and on the Company's website (www.detourgold.com). All figures are in Canadian dollars except where noted. Highlights
  • Detour Lake proven and probable open pit reserves of 15.5 million ounces contained gold
  • 21.7 years mine life with mill throughput increasing from 55,000 to 61,000 tpd in 2017
  • Life of mine average annual gold production of approximately 660,000 ounces at total cash costs of $723 per ounce sold(1)
  • Next five years average annual gold production of approximately 600,000 ounces at a total cash costs of $759 per ounce sold(1)
  • Life of mine sustaining capital of $1.14 billion plus $614 million for deferred stripping
  • Undiscounted pre-tax net cash flow of $6.5 billion and undiscounted after-tax net cash flow of $5.1 billion
  • Block A measured and indicated in-pit resources of 54 million tonnes grading 1.15 g/t, representing 2.0 million ounces of gold
"We are very pleased with this life of mine plan update for the Detour Lake mine," stated Pierre Beaudoin, COO of Detour Gold. "This improved mine plan demonstrates positive economics and, as we continue to optimize the operation, we certainly expect further improvements. Our technical team and external consultants have worked together to confirm the robustness of our block model and validating our mineral reserves. In addition, we have applied an elevated cut-off grade to maximize our return on investment. "The mine plan reflects our operating experience gained in the last two years in pioneering the pit and in the last year operating the process plant. The mine plan optimizes the first five years while addressing our operational risks. With the design modification to centerline, the tailings construction management allows effective decoupling from the mine with a transition to self-execution. The process plant throughput increase to 61,000 tpd is phased over a four year period. Our costs have started to decline and the trend will continue as we reach nameplate capacity (55,000 tpd). "Starting this year, we will be investigating a number of opportunities which could have a positive impact on costs and gold production. Detour Lake is a long-lived asset with potential for additional growth with the Block A project and continued regional exploration." Detour Lake Mine Assumptions and Parameters
Economic Assumptions

Prior(1) (09/2012)

Update (02/2014)

Gold price (US$/oz)

$

1,200(2)

$

1,200

Foreign exchange rate (US$/Cdn$)

1.00

1.10 (3)

Electricity ($/kWh)

0.065

0.05/0.08 (4)

Diesel fuel ($/l)

0.92

0.95

Income/mining tax rate (%)

25/10

25/10

Net Smelter Royalty (%)(5)

2.0

2.0 (5)

Mine Parameters
Ore milled (Mt)

470.0

476.4

Waste mined (Mt)

1,734

1,676

Strip ratio (waste:ore)

3.7

3.5

Average gold grade (g/t)

1.03

1.02

Total contained gold (M oz)

15.6

15.5

Estimated gold recovery (%)

91.0

92.2

Total recovered gold (M oz)

14.1

14.3 (6)

Mine life (years)

21.5

21.7

Average annual gold production (oz)

657,000

660,000

Costs
Sustaining capital ($ M)

1,156

1,143

Deferred stripping(7) ($ M)

-

614

Total cash costs before adj. below(8) ($/oz sold)

749

767

Less deferred stripping adjustment(7)

-

(44

)
Total cash costs(8) ($/oz sold)

749

723

 
(1) Refer to press release dated September 4, 2012 with Technical Report dated October 18, 2012.
(2) US$1,600/oz for 2013, US$1,500/oz for 2014, US$1,400/oz for 2015, and US$1,200/oz thereafter.
(3) Exchange rate of 1.05 for 2014, 1.07 for 2015, and 1.08 for 2016, and 1.10 for 2017 onwards.
(4) $0.05/kWh for 2014-19 and $0.08/kWh for 2020 onwards.
(5) 2% royalty is assumed to be paid in-kind.
(6) Includes approximately 58,000 ounces to be recovered from stockpiles as of December 31, 2013.
(7) The 09/2012 report excluded deferred stripping as the Company had not approved its deferred stripping accounting policy.
(8) Refer to the section on Non-IFRS Performance Measures at end of the press release. Total cash costs for 09/2012 based on gold ounces produced.
Detour Lake and Block A Mineral Resources The mineral resources are reported in relation to a conceptual open pit shell using a gold price of US$1,200 per ounce at a cut-off grade of 0.5 g/t Au for Detour Lake and 0.6 g/t Au for Block A. The mineral resource estimate is based on a geological block model prepared using the Ordinary Kriging (OK) method. This mineral resource was completed by SGS Canada Inc. in conformity with generally accepted definitions and guidelines given in the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards on Mineral Resources and Mineral Reserves (December 2005) as required by NI 43-101. Detour Lake Mineral Reserves The open pit mineral reserves were estimated within an engineered pit design by using the measured and indicated resources at an elevated cut-off grade of 0.5 g/t. This optimized pit shell and the engineered pit design are based on the cost and economic parameters estimated by BBA Inc. (gold price of US$1,000 per ounce and US$/Cdn$ exchange rate of 1.03). The proven and probable reserves include a mining dilution of 4% at 0.20 g/t(2) and a 5% ore loss to mining.

Mineral Resources and Reserves (December 31, 2013) (5)

 

Tonnes (Mt)

Grade (g/t Au)

Contained Gold (000's oz)

Reserves (1), (2), (3)
Detour Lake Mine Proven

94.4

1.29

3,901

Probable

379.7

0.95

11,585

P&P

474.0

1.02

15,486

Stockpiles

2.4

0.82

63

Total P&P

476.4

1.02

15,549

Resources (1), (3), (4)
Detour Lake Mine Measured (M)

16.4

1.37

725

Indicated (I)

65.9

1.01

2,150

M+I

82.4

1.09

2,874

Block A Measured (M)

1.5

1.21

57

Indicated (I)

52.5

1.15

1,934

M+I

53.9

1.15

1,991

Total M+I

136.3

1.11

4,866

Detour Lake Mine Inferred

19.2

0.75

465

Block A Inferred

2.5

1.23

99

Total Inferred

21.7

0.81

564

 
(1) Mineral reserves calculated using a gold price of US$1,000/oz; mineral resources calculated using US$1,200/oz. Foreign exchange rate of Cdn$1.03 to US$1.00.
(2) Mineral reserves estimated using a 4% dilution at 0.20 g/t Au (7% at 0.20 g/t Au for 2014) and 5% ore loss.
(3) Based on an elevated cut-off grade of 0.5 g/t Au for Detour Lake and cut-off grade of 0.6 g/t Au for Block A.
(4) Mineral resources are exclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
(5) Totals may not add due to rounding.
Mining and Production Total gold production over the life of mine is estimated to be 14.3 million ounces, averaging 660,000 ounces per year. The life of mine waste to ore ratio is estimated at 3.5 to 1. The Company continues to stockpile material grading between 0.4 to 0.5 g/t Au (estimated at 107.3 million tonnes averaging 0.45 g/t Au over LOM). This 'mineralized waste' is not included in the mineral resources or in the current mine plan. It could potentially be processed at the end of the mine life depending on the gold price environment. Mining rates are expected to average 252,000 tpd in 2014 and increase to a peak of 389,000 tpd in 2020. The haulage truck fleet is projected to increase from the current 23 to 41 trucks at the peak of the mine operation (2026-31) with no additional shovels beyond the current two electric rope shovels and three hydraulic shovels. The mining fleet will be supported by two smaller shovel/excavators. Processing Plant The processing plant is a conventional gravity, cyanidation and carbon-in-pulp facility designed to operate at 55,000 tpd. The front end of the circuit includes a large gyratory crusher with capacity of up to 90,000 tpd. The grinding circuit consists of two parallel lines, each having a twin pinion semi-autogenous (SAG) mill (36'X20'), a twin pinion ball mill (26'X40.5'), and a secondary and pebble crusher. Summary of the annual mine production plan:
Years

Ore Mined (kt)

Ore Milled (kt)

Head Grade (g/t)

Production (oz)

Waste (kt)

Strip ratio

2014

21,691

19,000

0.87

490,254

70,459

3.25

2015

22,942

20,075

0.91

542,610

78,455

3.42

2016

21,301

21,301

0.93

588,112

99,989

4.69

2017

22,265

22,265

1.04

684,832

107,166

4.81

2018

22,265

22,265

1.04

685,933

115,814

5.20

2019

22,265

22,265

0.83

542,560

119,136

5.35

2020

22,265

22,265

0.86

565,359

119,596

5.37

2021

22,265

22,265

0.95

627,201

118,082

5.30

2022

22,265

22,265

0.88

577,384

112,970

5.07

2023

22,265

22,265

1.01

668,434

105,940

4.76

2024

22,265

22,265

1.00

658,966

87,844

3.95

2025

22,265

22,265

1.02

670,201

79,344

3.56

2026

22,265

22,265

0.89

582,933

74,536

3.35

2027

22,265

22,265

0.99

650,690

73,869

3.32

2028

22,625

22,265

1.11

731,842

72,571

3.26

2029

22,265

22,265

0.99

655,740

62,596

2.81

2030

22,265

22,265

1.12

741,684

63,397

2.85

2031

22,265

22,265

1.09

719,348

53,555

2.41

2032

22,265

22,265

1.24

822,519

25,932

1.16

2033

22,265

22,265

1.24

823,485

22,672

1.02

2034

22,265

22,265

1.25

828,874

10,269

0.46

2035

7,320

15,293

1.05

474,499

1,557

0.21

Total

474,024

476,439

1.02

14,333,459

1,675,751

3.54

The 2014 plan is to ramp up to 55,000 tpd in the last quarter of 2014 (average of 52,000 tpd for the year). The life of mine gold recovery is estimated at 92%. The gold recovery was increased by 1% based on actual results from the fourth quarter of 2013 where recovery was 1.5% above feasibility level (91%). The Company will also be initiating a step-by-step process (over the next four years) to gradually increase throughput to 61,000 tpd in 2017. Operating Costs Total cash costs over the life of mine are projected to average $723 per ounce of gold sold(3). The updated cash operating costs are based on current market prices for consumables and all other mine benchmarking such as current costs at the mine site.
Life of Mine

$/t milled

$/t mined

$/oz sold

Mining costs

11.55

2.56

392

Processing cost

7.82

-

266

General and administration

2.44

-

83

Sub-total

21.81

-

741

Other adjustments

-

-

(18

)
Total cash costs (LOM) (1)

-

-

723

 
(1) Other adjustments include costs for deferred stripping, agreements with Aboriginal communities, refining charges and are net of silver by-product credits.
Sustaining Capital Expenditures Sustaining capital expenditures over the operation's mine life are estimated at $1.14 billion plus $614 million for deferred stripping (excludes $70 million for mine closure).
Sustaining Capital

Period 2014-18 ($ millions)

Life of mine ($ millions)

Mining

168

535

Process plant

71

126

Tailings management

203

454

G&A

14

28

Total

456

1,143

Mine closure

70

Deferred stripping

226

614

Economic Sensitivity Analysis The economic cash flow model is based on a gold price of US$1,200/oz and generates an undiscounted pre-tax and after capital life of mine net cash flow of $6.5 billion and after-tax net cash flow of $5.1 billion. Using a discount rate of 5% the discounted pre-tax and after capital life of mine net cash flow produces a discounted cash flow of $3.4 billion and after-tax net cash flow of $2.8 billion. The project economics are most sensitive to changes in the gold price, the Canadian and US dollar exchange rate and operating cost changes.