Skip to content

Daytime Snow Removal Plan of Operation – East Highway 655 – Week of March 2nd, to March 6th, 2015.

  The Public Works Department wishes to inform the public that crews will be doing snow removal in Timmins, East of Highway 655, from March 2nd, to March 6th, 2015. […] The post Daytime Snow Removal Plan of Operation – East Highway 655 – W

 

The Public Works Department wishes to inform the public that crews will be doing snow removal in Timmins, East of Highway 655, from March 2nd, to March 6th, 2015.

  1. Monday March 2nd, – Connaught Hill Area- Dunn, Leighton, Allan, Evans, Warner
  2. Tuesday March 3rd, – William, Cecil, Powell, O’Brian
  3. Wednesday March 4th – Broadway, Essa, Dome, Shamrock
  4. Thursday March 5th – To be determined
  5. Friday, March 6th – Strachan, Crawford, Main 

A.  Note on the Plan: The above plan or parts of the plan may be changed at any time and/or delayed if a winter storm is in effect or related to mechanical issues. The snow removal crew will change to a snow plowing operation. Those streets that may not be done will be done on the next available snow removal shift.

B.  Illegal placement of Snow from Residential Property onto Sidewalk and Road: A reminder that City BYLAW 1993-4162 does not allow a person to place snow from a person’s property and place onto the road or sidewalk.

C.  Posted No Parking Signs Advising Winter Maintenance: We would like to remind residents that Public Works will be posting colour coded No Parking Signs notifying that Winter Maintenance will be taking place. Vehicles will be ticketed and towed to allow for Snow Removal Crew to advance.

D.   Winter Parking Ban: A reminder that the Winter Parking Ban is effect and parking on the street is not permitted on any day, between the hours of 23:30hrs to 07:30hrs, from November 1st through April 30th

E.  Priority Sequence for Snow Removal Operations:

 a.     Day Operation:

  1. Snow removal is never done in the area where Sanitation is taken place.
  2. High density residential areas (Older Section of City: one-ways, narrow streets);
  3. Low density residential areas

b.    Night Operations:

  1. Highway sections;
  2. High density commercial sections;
  3. Main Arterial Routes 

F.  Safety: A reminder to respect safety signage as the safety of workers is very important.  

We thank you for your cooperation in this matter.

Manager of Public Works

705-360-2646

The post Daytime Snow Removal Plan of Operation – East Highway 655 – Week of March 2nd, to March 6th, 2015. appeared first on City of Timmins.